a.
Introduction
(1)
To reduce the overall weight and dimensional envelope of the launcher, it has been
designed for easy and rapid sectionalization. The crane, Tail lift and slide frame based
launcher and A-Frame stabilizer feet are all removable. This is achieved through the use
of quick disconnect hydraulic hoses, plug and socket electrical connections and wide use
of simple pinned mechanical attachments. Lifting and tie-down points are provided on the
crane and launcher to aid lifting.
(2)
Sectionalization of the launcher can be achieved within 1 hour and should be performed as
outlined in the section below.
b.
DSB Far Bank Support Removal
To remove the far bank support follow the procedure below:
NOTE
The Numbers on the diagrams refer to the Paragraph Numbers of the Text.
(1)
Release A-Frame shoot bolts and remove left and right hand mudguards
|