TM 9-2320-211-34-2-1
1.
Turn over differential carrier assembly (1).
2.
W r a p a length of string (2) around spur gear pinion (3) as shown. Join string
t o bearing preload scale (4).
3.
Using bearing preload scale (4), check preload. If new bearings were put in
c a p assembly (5), preload must be 12 to 18 poundinches. If original bearings
w e r e used, preload must be 4 to 8 poundinches.
4.
Turn over differential carrier assembly (1).
IF PRELOAD IS NOT WITHIN LIMITS GIVEN, GO TO FRAME 22.
IF PRELOAD IS WITHIN LIMITS GIVEN, GO TO FRAME 23