TM 9-2320-211-203-2
MAINTENANCE OF MATERIAL USED IN CONJUNCTION
WITH MAJOR ITEMS
Section I. SCOPE
21-1. EQUIPMENT ITEMS COVERED. This chapter gives equipment maintenance
procedures for winterization kits, deep water fording kit, and special purpose kits
for which there are authorized corrective maintenance tasks at the organizational
maintenance level.
maintenance is authorized at the organizational maintenance level are covered in
this chapter.
Section II.
WINTERIZATION KITS
AND TEST.
WARNING
Smoking, sparks, or open flame are not allowed
within 50 feet of work area during this task.
TOOLS:
General mechanic tool kit
Flat-tip screwdriver
6-inch pliers
1/2-gallon container
Solvent, dry cleaning, type II (SD-2), Fed. Spec P-D-680
SUPPLIES:
Fuel pump cover gasket
Fuel pump cup gasket
Rags
PERSONNEL:
Two
EQUIPMENT
CONDITION: Truck parked, engine off, handbrake set.
a.
Preliminary Procedures.
(1) Disconnect battery ground cable. Refer to Part 1, para 7-44.
(2) Turn off personnel heater, powerplant heater, and shutoff cocks. Refer
to TM 9-2320-211-10.
|