TM 5-5420-279-23
1
2
4
3
a.
Remove
(1)
Ensure that he crane is in the stowed position.
(2)
De-pressurize the hydraulic system. See unit maintenance procedure 5-118.
(3)
Remove the electrical cable (2) to the pressure transducer (1).
(4)
Remove the hydraulic connections (3 and 4).
(5)
Remove the pressure transducer (1).
(6)
Check all threaded components for damage.
(7)
Check the electrical cable for damage.
(8)
Replace components as necessary.
b.
Install
(1)
Fit the pressure transducer (1) to the lift cylinder.
(2)
Fit the hydraulic connections (3 and 4) to the pressure transducer (1).
(3)
Fit the electrical cable (2) to the pressure transducer (1).
(4)
Switch the battery shutoff switch to the on position.
(5)
Operate the crane in accordance with the operator's manual TM 5-5420-279-10.
(6)
Run the crane to overload on full extension with maximum load plus 5-8%.
6-248
|