TM 5-5420-279-23
b.
Install
(1)
Fit the support assembly crane. See direct support maintenance procedure 6-055.
(2)
Fit the rotate gear. See direct support maintenance procedure 6-047.
(3)
Fit the rotate hydraulic coupling. See direct support maintenance procedure 6-046.
(4)
Fit all electrical and hydraulic lines to the crane base in the positions noted during removal.
(5)
Fit the seat assembly. See unit maintenance procedure 5-145.
(6)
Fit the lift cylinder. See direct support maintenance procedure 6-050.
(7)
Fit the boom. See direct support maintenance procedure 6-057.
(8)
Fit the jib cylinder. See direct support maintenance procedure 6-051.
(9)
Fit the boom jib. See direct support maintenance procedure 6-061.
(10)
Fit the jib extension assembly. See direct support maintenance procedure 6-062.
(11)
Fit the jib extension cylinders. See direct support maintenance procedure 6-053.
(12)
Lubricate all parts of the crane that have grease fittings (4, 15 and 16).
c.
Follow on tasks
(1)
Switch the battery shutoff switch to the on position.
(2)
Check the operation of the crane and check for leaks.
|