TB 1-1520-240-20-147
b. If the wiring harness has not been properly assembled and installed, clear the red dash //--// entry
required by paragraph 1A and enter the following red diagonal \\/\\ "Fuel control relay wiring harness improper-
ly installed"
c. Make the following circle red //X// entry on the 2408-13-1 "A/C restricted to flights below 6000' MSL
IAW CH-47-02-ASAM-03 (TB 1-1520-240-20-147)". Perform correction procedures in accordance with para-
9. Correction Procedures.
a. If a replacement box is available, remove and replace the fuel pump relay box in accordance with
TM 55-1520-240-23-8, task 116.1 and task 116.2.
b. If a replacement box is not available, call the technical point of contact for wiring harness repair in-
structions.
c. Once discrepant boxes have been replaced or wiring harness repaired, the red diagonal \\/\\ and
circle red //X// entries will be cleared.
a. Parts Required. Items cited in paragraph 12c may be required to replace defective items.
b. Requisitioning Instructions. Requisition replacement parts using normal supply procedures. All req-
uisitions shall use project code (CC 57-59) "X1U" (X-RAY--ONE--UNIFORM).
NOTE
Project code "X1U" is required to track and establish a database of stock fund expenditures in-
cuured by the field as a result of message actions.
c. Bulk and Consumable Materials.
Terminal, lug BACT12AC2
5950-00-204-8966
d. Disposition. Dispose of any discrepant part/component through the normal supply system .
e. Disposition of Hazardous Material. N/A.
11. Special Tools and Fixtures Required. N/A.
12. Application.
a. Category of Maintenance -- AVUM. Aircraft downtime will be charged to AVUM. Report aircraft non-
mission capable maintenance (NMCM) while undergoing inspection and correction in accordance with this
message. Report aircraft non-mission capable supply (NMCS) while waiting for parts in accordance with this
message.
b. Estimated Time Required.
(1) Time to complete inspection --
(a) Total of 0.5 man-hours using 1 person
(b) Total of 0.5 hours downtime for one end item.
(2) Time for repair/replacement --
(a) Total of 3 man-hours using 3 persons.
(b) Total of 1 hour downtime for one end item.
c.
Estimated Cost Impact to the Field.
NOMENCLATURE
PART NUMBER/
QUANTITY
COST EACH
TOTAL $
NATIONAL STOCK NUMBER
Relay, assembly
145E2195-1
1
$6428.80
$6428.80
Terminal, lug
BACT12AC2
32
$5.50 HD
$1.76
5940-00-204-8966
Total cost per aircraft = $6430.56