|
|
TM 9-2320-366-20-2
TM
CONTINUITY TEST
(1)
Remove BOOM UP/DOWN controller (para 7-32).
(2)
Set multimeter to ohms.
(3)
Connect positive (+) probe of multimeter on pin
M of remote control box connector.
(4)
Connect negative (-) probe of multimeter on pin
4 of BOOM UP/DOWN controller internal
wiring harness and note reading on
multimeter.
(5)
Connect positive (+) probe of multimeter on pin
H of remote control box connector.
(6)
Connect negative (-) probe of multimeter on pin
1 of BOOM UP/DOWN controller internal
wiring harness and note reading on
multimeter.
(7)
If continuity is not present, replace remote
control box internal wiring harness (para 7-32).
(8)
If continuity is present, replace BOOM
UP/DOWN controller (para 7-32).
(9)
Install BOOM UP/DOWN controller (para 7-32).
(10)
Close cover on junction box.
(11)
Tighten four screws on junction box cover.
(12)
Stow crane (TM 9-2320-366-10-1).
2-1219
|
Privacy Statement - Press Release - Copyright Information. - Contact Us |