TM 9-2320-211-34-2-1
FRAME 5
1.
W r a p a length of string (1) around retainer assembly (2) as shown. Join
s t r i n g to bearing preload scale (3).
2.
Using bearing preload scale (3), check preload. If new bearings were put in
r e t a i n e r assembly (2), preload must be 12 to 18 pound-inches. If original
b e a r i n g s were used, preload must be 4 to 8 pound-inches.
T a k e off string (1) and bearing preload scale (3).
3.
IF PRELOAD IS NOT WITHIN LIMITS GIVEN, GO TO FRAME 6.
IF PRELOAD IS WITHIN LIMITS GIVEN, GO TO FRAME 8
9-46
|